Water Treatment and Servicing Master Plan - Municipal Class Environmental Assessment - Notice of Study Completion

May 12, 2025 - 12:49pm
Type
Public Notices

TAKE NOTICE that the Township of Tiny has completed a Master Plan Class Environmental
Assessment (Master Plan) for the supply of municipal drinking water to existing and future
residents in serviced areas. The Master Plan identifies the preferred solutions to increase the resiliency of the township’s 16 municipal drinking water systems and to accommodate the anticipated growth to the year 2045.

The Master Plan was prepared in accordance with the Master Plan requirements following
Approach No. 1 of the Municipal Engineers Association (MEA) Municipal Class Environmental
Assessment (as amended in 2023). The list of recommended projects with their Class EA
Schedules is shown below.

The Final Draft of the Master Plan is posted for review on the Township of Tiny project
webpage at: www.tiny.ca/WaterMasterPlan. Comments can be submitted by using the online comment form on the project webpage or by email to the contact below. Comments will be accepted until June 13, 2025, and will be taken into consideration and included in the Final Report. Comments and information received during this Class EA are collected in accordance with the Municipal Freedom of Information and Protection of Privacy Act. All comments will be part of the public record.

Jason Covey 
Tatham Engineering Limited
115 Sanford Fleming Drive, Suite 200
Collingwood, Ontario, L9Y 5A6 
E: jcovey@tathamen.com 
T: 705-444-2565 ext. 2018

Jean-François Robitaille
Township of Tiny
130 Balm Beach Road West 
Tiny, Ontario, L0L 2J0
E: jrobitaille@tiny.ca 
T: 705-526-4204 

If concerns that this Class EA Update may have potential adverse impacts on protected
Aboriginal and treaty rights that cannot be resolved in discussions with the Township of Tiny, a person or party may request the Minister of the Environment, Conservation and Parks (MECP) issue an order for a project to comply with Part II of the Environmental Assessment Act (Section 16(6)) or meet further conditions. Section 16(6) Order requests must be sent to the Minister and to the Director of Environmental Assessment Branch at the addresses below. A copy of the request must also be sent to the contacts above.

Minister, MECP
777 Bay Street, 5th Floor
Toronto, Ontario, M7A 2J3 
Minister.mecp@ontario.ca 

Director, Environmental Assessment Branch, MECP 
135 St. Clair Avenue West, 1st Floor 
Toronto, Ontario, M4V 1P5
EABDirctort@ontario.ca 

If there is no Section 16(6) Order request received by June 13, 2025, the Township intends to
proceed to further Class EA, design and implementation of the recommended projects as per the Final Master Plan Report, and subject to planning, priorities and Council approval.

 

Project DescriptionClass EA
Schedule
Comments
Short Term Projects
Replace wells at Georgian Bay Estates PH 19ExemptPublic advised prior to implementation
Connect Georgian Bay Estates and Sawlog Bay
distribution systems
ExemptPublic advised prior to implementation
Construct standby well in Lafontaine DWSExemptPublic advised prior to implementation
Construct standby well at Rayko PH 6ExemptPublic advised prior to implementation
Increase standby well supply at Perkinsfield PH 26ExemptPublic advised prior to implementation
Add standby power at Perkinsfield PH 22ExemptPublic advised prior to implementation
Add standby power at Bluewater PH 8ExemptPublic advised prior to implementation
Add standby power at Wyevale BPS 24ExemptPublic advised prior to implementation
Long Term Projects
Construct standby well at Bluewater PH 8ExemptPublic advised prior to implementation
Expand Bluewater PH 18 reservoir (for fire protection)ExemptPublic advised prior to implementation
Replace Cook’s Lake Well 12-2 with higher capacity wellExemptPublic advised prior to implementation
Construct new well and PH at Tee Pee PointSch. BClass EA study to be completed
Expand reservoir and upsize high lift pumps at Wyevale
BPS 24 (for fire protection)
ExemptPublic advised prior to implementation
Construct standby well at Castle Cove PH 4ExemptPublic advised prior to implementation
Add watermain loops in Georgian Bay Estates DWSExemptPublic advised prior to implementation